Grading work, including a temporary windrow of class 5 in the middle of the roadway until it is hauled to a stockpile. Please exercise caution and patience. This should be removed within one day.
Completion of the storm sewer work on phases 2 and 3 may interrupt some travel in the areas. If there will be limited access to your driveway, someone will knock on your door to notify you to move your vehicle prior to digging. Minimal impacts are anticipated and prevention of impacts are in place.
Expect some delays due to weather; however, phase 1 is still on schedule for completion.
June 5
Curb and gutter is delayed to June 5 due to anticipated rain the week of May 30 and slower than expected storm sewer installation.